0:03

it is a common occurrence for an oil and

0:05

gas operator organization to bring on a

0:08

well after initial Drilling and

0:10

completion or after a workover and

0:12

observe that the production rate is not

0:14

as expected if rates are greater than

0:17

expected there is some interest and

0:19

evaluation as to why and a study May

0:22

commence action is often limited to

0:25

observing possible rate decline say

0:27

waiting two or 3 months and then

0:30

assessing production performance but

0:32

this outcome contrasts greatly to the

0:35

scenario where initial production from a

0:37

newly started up well is less than

0:39

expected not accurately identifying the

0:42

correct cause or causes of less than

0:45

expected production will often lead to

0:47

costly remedial attempts that likely

0:50

will result in the failure to achieve a

0:52

Well's maximum productive capacity

0:55

conversely proper investigative studies

0:58

that lead to identification of true

1:00

formation damage will provide the

1:02

engineer with proven remediation tools

1:05

to regain well productivity if acidizing

1:08

a formation is chosen as a remediation

1:11

step to take the stimulation design

1:13

engineer must also understand corrosion

1:16

control iron control acid diversion Etc

1:20

to achieve Optimum stimulation results

1:24

poor corrosion control practices can

1:26

lead to catastrophic failure of well

1:28

completions Elemental iron is often

1:31

present throughout a reservoir lithology

1:34

and ignoring the effects of iron that

1:36

goes into solution during an acid job to

1:39

restore productivity can readily turn a

1:41

successful acid job into a failure this

1:44

is due to the precipitation of iron as

1:47

pH Rises during Flowback and cleanup

1:50

following an acid job if proper acid

1:54

diversion techniques are not properly

1:56

analyzed and designed as a fundamental

1:58

component of an acid job job the acid

2:01

pumped may just react the most permeable

2:03

portions of the reservoir thus leading

2:06

to job failure the chemistry of

2:09

limestone and Sandstone remedial acid

2:12

job treatments to restore production

2:14

differ greatly this proper rock

2:16

minerology identification and lab

2:19

testing with acid processes is mandatory

2:22

in restoring lost production properly

2:25

identifying formation damage and

2:27

applying remedial actions will provide

2:30

the opportunity to restore a well to its

2:32

maximum

2:34

productivity

Continue with YouTLDR

Analyze another video with Pro

Process a new video, search every timestamp, compare sources, and keep the result in your library.

Get Pro — $12/month30-day money-back guarantee

More transcripts

Explore other videos transcribed with YouTLDR.